YIKES! Jean and I received an update from our contractor that construction could drag out until October 1.
They are still not even sure when the new lights for the store will arrive.
Here is where things stand:
By Friday, September 12
- Complete retail floor finish.
- Complete electrical rough-in and framing.
- We can begin to move some shelving this week.
By Friday, September 19
- Drywall completed,
- new toilet room plumbing inspected
- concrete poured
- Train layout and Slot Car track moved.
- More shelving moved.
By Friday, September 26
- Finish drywall
- painting
- cabinets
- doors
- install lights
- Shelving and cash registers moved
- Close Petaluma store?
Wednesday, October 1
- Final inspections
- repairs
- clean up
- Ready to Occupy!!!
Sunday, October 5
- Shelves stocked
- computers running
- ready to open!!
October Grand Opening Celebration!
We will announce a date after we get everything checked out.